Determining liability for environmental damage requires identifying the loss that compensation is intended to address. Compensating the owner of contaminated land for its diminished value does not establish that local water resources have been cleaned or that conditions necessary to sustain wildlife have been restored. Compensation for financial loss and restoration of the environment require distinct assessments. In arbitration, the question is how this distinction should inform the relief sought, the taking of evidence and the content of the award.
European Union (EU) environmental directives establish criteria concerned with protecting damaged natural resources and restoring their functions. Their relevance to arbitration cannot rest on the assumption that the directives themselves confer jurisdiction on arbitrators. This article examines the relationship between compensation and restoration in private law disputes capable of settlement by arbitration. It argues that contractual remediation obligations should be linked to measurable environmental outcomes and supported, from the outset, by arrangements securing their performance.
I. Distinguishing Compensation from Environmental Remediation under European Union Directives
The Environmental Liability Directive governs the prevention and remediation of specified forms of environmental damage in accordance with the polluter pays principle. Its scope is distinct from that of a general compensation regime covering all economic loss. The relevant categories and thresholds of damage must be examined separately for protected species, natural habitats, water and land. Damage to private property or personal injury should not be treated as interchangeable with deterioration of the environment itself.¹
For damage to water, protected species and natural habitats, the Directive provides for three forms of remediation. Primary remediation seeks to return damaged natural resources and their functions towards their baseline condition. Complementary remediation addresses situations in which primary remediation does not achieve full recovery. Compensatory remediation addresses interim losses arising before recovery is complete. Land damage is governed by separate requirements concerning the removal of significant risks to human health. The distinction between compensatory remediation and monetary compensation payable to individuals is particularly significant for arbitration. Where a wetland takes years to recover, calculating the cost of decontamination alone may be insufficient. The ecological functions lost during that period must also be considered. This does not, however, mean that any individual may claim the monetary equivalent of ecological loss for their own benefit. The legal basis of the entitlement to relief must be established independently.²
Failure to meet the Directive’s threshold of environmental damage does not establish that all private law claims are unavailable. A contract may prescribe a more demanding standard of environmental quality. A dispute may consequently concern breach of contract independently of liability under the Directive. Conversely, adopting a less demanding contractual standard cannot displace mandatory environmental obligations.
The Water Framework Directive’s obligation to prevent deterioration connects remediation with the conditions governing project authorisation. The Court of Justice of the European Union has held that, unless the conditions for a derogation are satisfied, authorisation must be refused for projects liable to cause deterioration in the status of a body of surface water. An agreement allocating costs between an operator and a contractor therefore does not determine whether the project may lawfully proceed. Nor does payment of compensation automatically render the continuation of an environmentally unlawful activity permissible.³
The Environmental Impact Assessment Directive governs project assessment, public participation and necessary monitoring measures. Information obtained through these procedures may assist an arbitral tribunal in assessing the extent of damage and compliance with contractual obligations. The preparation of an assessment report does not, however, establish the absence of subsequent damage. The tribunal should compare the report’s assumptions with the effects that actually occurred; a permit should not be treated as providing blanket immunity from liability.⁴
The implications of these directives for contractual relationships must be determined by reference to their implementation in national law and the applicable law. The Environmental Liability Directive neither grants private parties an independent right to compensation nor transfers the competent authority’s responsibility for determining remedial measures to arbitrators. Administrative obligations, contractual restoration duties and an injured party’s compensation claim must therefore be considered separately. Their common factual origin does not make them interchangeable.⁵ The distinction drawn by the English legal philosopher Herbert Lionel Adolphus Hart between primary and secondary rules provides a useful explanation. The existence of an environmental obligation and the authority to issue a binding determination concerning that obligation are separate questions. Applying Hart’s distinction between rules imposing duties and rules conferring powers requires distinguishing an arbitrator’s consideration of environmental damage from an award granting relief that was not sought or directing action beyond the tribunal’s jurisdiction.⁶
II. Claims for Environmental Restoration in Arbitration and Implementation of the Award
The determination of a restoration claim in arbitration depends on the scope of a valid arbitration agreement, the arbitrability of the dispute and the substantive legal basis of the claim. The existence of an environmental obligation owed by one company does not establish that another company may demand every conceivable form of remediation. The tribunal must identify who is entitled to require which performance, applying the relevant conditions governing specific performance or reparation in kind. Two claims must be distinguished where a contractor entrusted with environmental remediation breaches its contract. A demand for completion of the agreed decontamination works concerns performance of the contractual obligation. A claim concerning additional environmental damage caused by the contractor may depend on different conditions of liability. Although both claims may result in physical restoration, their legal bases, evidential requirements and scope of liability may differ.
This distinction also determines the questions referred for expert examination. Experts should not merely be asked to calculate an aggregate monetary loss. They should address the source of contamination, the previous environmental condition, feasible restoration methods and the anticipated recovery period. The procedures developed by the Permanent Court of Arbitration for environmental disputes accommodate scientific expertise and technical evidence. The ultimate determination of legal liability nevertheless remains the responsibility of the tribunal.⁷
An award directing restoration must specify an obligation capable of performance. It should identify the boundaries of the contaminated area, the required works, the applicable deadlines and the criteria for completion. A general reference to environmental protection does not explain what conduct will discharge the obligation. Equally, an award that disregards necessary administrative authorisations or requires works on third-party land without the requisite consent cannot provide an effective remedy.
A restoration claim must also be assessed against the applicable law’s requirements concerning impossibility and disproportionate cost. The expense of intervention does not, by itself, establish that monetary compensation is sufficient. The assessment should compare the environmental benefits of remediation, the duration of the damage and feasible alternatives. The debtor’s commercial preferences should be distinguished from legally recognised impediments to performance. Ecological benefits should not be measured exclusively by increases in the market value of land.⁸
The contractual arrangement proposed here would define three elements of the restoration obligation at the outset: the environmental outcome to be achieved, the method for verifying that outcome and the legal consequences of non-performance. Completion of decontamination works should not, for example, depend solely on the contractor’s declaration that its activities have ended. Agreed measurements should be subject to independent verification. The criteria must remain consistent with the competent authority’s requirements; the contract must not reduce the legally required level of environmental protection.
Financing restoration should form part of the same arrangement. The parties may provide for a bank guarantee or legally protected funds earmarked for use under specified conditions. They may agree that access to this security need not await a final determination of liability, provided that the conditions for payment and subsequent accounting are clearly defined. This separates the financing of urgent intervention from the final allocation of expenditure. The proposal should not be presented as an existing obligation imposed on all operators by the directives.⁹
Where the debtor fails to undertake restoration, consideration may be given, insofar as the applicable law permits, to performance by a third party and recovery of reasonable costs from the debtor. The award must clearly explain how this possibility is to operate. A direction permitting unrestricted recovery of indeterminate future expenditure would undermine legal certainty. The same restoration expenditure must also be prevented from being recovered twice, once as damages and again as the cost of substitute performance.
Expedited procedures can support this approach. Mediation may facilitate agreement on the restoration method and allocation of expenditure; if agreement cannot be reached, arbitration can provide a binding determination. Negotiation periods should not, however, obstruct applications for urgent relief. Expert examination, interim measures and the coordinated use of different dispute resolution methods, discussed in the International Chamber of Commerce’s relevant report, offer procedural tools that can address these needs.¹⁰
Cross-border enforcement requires separate consideration. The Convention on the Recognition and Enforcement of Foreign Arbitral Awards, commonly known as the New York Convention, provides the principal framework for recognising and enforcing foreign arbitral awards; it does not eliminate scrutiny of arbitrability or public policy. For non-monetary obligations in particular, the enforcement mechanisms available under the law of the enforcing jurisdiction matter. An award cannot automatically impose obligations on persons who are not parties to the arbitration agreement or extinguish their independent rights of action.¹¹
The contribution of arbitration to resolving environmental disputes should not be measured by the amount of compensation awarded. The decisive consideration is whether it delivers relief that is both legally available and practically effective. Connecting the environmental recovery criteria contained in European Union directives with contractual obligations can serve this purpose. An approach addressing the substance, financing and verification of restoration together can provide legal protection directed towards the recovery of ecological functions, while giving those responsible clearly defined and enforceable obligations.
Footnotes
- European Commission, Environmental Liability, sections entitled “Defining Environmental Damage” and “Determining Liability for Environmental Damage”, concerning the distinction between the Directive’s public remediation regime and private law damage.
- European Parliament and Council, Directive 2004/35/EC of 21 April 2004 on environmental liability with regard to the prevention and remedying of environmental damage, Article 3(3) and Annex II, sections 1, 1.1.1–1.1.3 and 2. On the determination of baseline condition, see also Article 2(14).
- European Parliament and Council, Directive 2000/60/EC establishing a framework for Community action in the field of water policy, Article 4; Court of Justice of the European Union, Bund für Umwelt und Naturschutz Deutschland e.V. v Bundesrepublik Deutschland, Case C-461/13, judgment of 1 July 2015, especially paragraph 51.
- European Parliament and Council, Directive 2011/92/EU on the assessment of the effects of certain public and private projects on the environment, as amended by Directive 2014/52/EU, Articles 3, 5, 6 and 8a(4).
- Directive 2004/35/EC, Articles 3(3), 7(2) and 11. These provisions distinguish private compensation claims from the competent authority’s responsibility for determining remedial measures.
- Hart, Herbert Lionel Adolphus, The Concept of Law, 3rd ed., Oxford University Press, Oxford, 2012, pp. 91–99. The application of Hart’s conceptual distinction to environmental remediation and arbitral jurisdiction is the analysis developed in this article.
- Permanent Court of Arbitration, Environmental Dispute Resolution, section entitled “Specialized Environmental Rules for Arbitration and Conciliation”, concerning scientific expertise, the assessment of evidence and tribunal-appointed experts.
- For comparison, International Institute for the Unification of Private Law (UNIDROIT), Principles of International Commercial Contracts 2010, Article 7.2.2 and accompanying commentary. For the assessment of environmental remediation options, see also Directive 2004/35/EC, Annex II, section 1.3. Applying these criteria in a particular arbitration requires an appropriate legal basis.
- Directive 2004/35/EC, Article 14(1). The provision encourages the development of financial security instruments; the contractual financing arrangement described in the text is the solution proposed in this article.
- International Chamber of Commerce, Resolving Climate Change Related Disputes through Arbitration and ADR, Paris, 2019, especially pp. 20–25, 29–33 and 35–37. In the report’s title, ADR denotes alternative dispute resolution.
- Convention on the Recognition and Enforcement of Foreign Arbitral Awards, New York, 10 June 1958, Articles II, III, V(1)(a)–(c) and V(2).