International Arbitration of Breaches of Environmental Commitments: Burden of Proof, Damages and Specific Performance
International Arbitration of Breaches of Environmental Commitments: Burden of Proof, Damages and Specific Performance

International Arbitration of Breaches of Environmental Commitments: Burden of Proof, Damages and Specific Performance

In international arbitration, a claim arising from a breach of an environmental commitment requires more than an allegation that the contractual result was not achieved. The tribunal must identify the nature of the obligation, the period in which the breach occurred and the legal basis for the relief sought. The distinction between an undertaking to achieve a specified result and an obligation of best efforts is one starting point for that inquiry.[1] A treatment plant’s failure to deliver the specified water quality or energy equipment’s consumption of resources beyond the guaranteed level may generate arbitral claims under different contracts.[2] Technical expertise does not displace the tribunal’s responsibility to assess the parties’ claims and defences as matters of law. The protection available through arbitration depends on a reasoned connection between the facts alleged and the relief requested.

The central procedural challenge in arbitrating environmental commitments is reconciling difficulties of proof with a fair hearing. Operational data are frequently held by the respondent, while the assessment of loss may depend on records belonging to other facilities, suppliers or public authorities. Rules governing the production of evidence can help manage this information asymmetry, but do not themselves establish substantive liability.[3] The procedure adopted by the tribunal should make clear which facts are disputed and which matters the parties must address. The International Chamber of Commerce’s 2026 Arbitration Rules require the tribunal to act fairly and impartially and afford each party a reasonable opportunity to present its case.[4] When these safeguards are maintained, technical complexity need not become a reason to dismiss the claim or award speculative damages. Instead, it becomes a concrete factor informing the conduct of the proceedings.

I. Burden of Proof and the Assessment of Technical Evidence in Arbitration

The first question in an environmental performance dispute is which information can establish contractual non-performance. An annual sustainability report may not, by itself, explain a water limit exceeded during a particular week or the incorrect operation of a cooling unit. Measurement records, maintenance documents, acceptance tests and workload distribution data perform different evidential functions. The International Bar Association’s 2020 Rules on the Taking of Evidence in International Arbitration can provide a framework for producing these materials when the parties agree to their application or they are otherwise adopted procedurally.[5] The Rules should not be assumed to apply automatically; the evidentiary arrangements should be clearly established at the beginning of the arbitration.

The allocation of the burden of proof must be distinguished from access to evidence. Article 27 of the United Nations Commission on International Trade Law’s Arbitration Rules requires each party to prove the facts on which it relies to support its claim or defence.[6] In arbitrations to which those Rules do not apply, the burden must be determined under the relevant substantive and procedural framework. The respondent’s possession of environmental data does not automatically reverse the burden in all its aspects. It may, however, make document production and expert examination necessary. Arbitrators should distinguish the breach alleged by the claimant from the specific facts on which the respondent relies to avoid liability. Organising the evidence around that distinction can prevent a party from being required to defend its entire operational archive against indeterminate allegations.[7]

It must be established whether a limit in a technical schedule relates to acceptance testing or continuing operation. Equipment that conforms at delivery may subsequently fail because of deficient maintenance. Conversely, an initial test conducted under unsuitable conditions may have concealed an original defect.[8] The relevant records and the party potentially liable will differ in those situations. A claimant alleging that a technical result was not achieved should explain the period covered by the obligation. A respondent’s defence based on faulty maintenance or misuse should likewise be substantiated by showing how far the alleged conduct affected the outcome. Otherwise, technical possibilities take the place of examining what actually occurred.[9]

A request for document production in arbitration should be limited by the fact to be proved and the document’s connection with the outcome of the dispute. The International Bar Association’s Rules set criteria for identifying requested documents and explaining their relevance.[10] A request for the entire technical archive should therefore not be assessed in the same way as a request for meter records covering a specified period. The tribunal may scrutinise the explanations of the party controlling the information and consider an adverse inference permitted by the Rules where documents are withheld without satisfactory explanation.[11] Any such inference must remain connected to the fact that the missing document could establish. Failure to produce a maintenance record does not justify automatically accepting every head of loss or the amount claimed. Assessment of procedural conduct must not displace examination of the elements of substantive liability.

Comparability is a basic condition of reliable assessment of environmental data. Comparing consumption figures from two facilities operating at different capacities, in different climates or for different periods may be misleading. The expert’s task is to provide the technical basis for explaining which information corresponds to the legally relevant contractual condition.[12] A normalisation method must nevertheless not operate as an assumption that disregards actual consumption. If the contract imposes an absolute volume limit, a result that could hypothetically have been achieved under more favourable conditions does not prove performance. The comparison must be structured first by the nature of the obligation and then by the technical method.[13]

An electronic record’s evidential character cannot be determined solely from its file format. The device that generated the data, the timing of amendments and the persons able to process them all matter. Disclosure of subsequent corrections to contemporaneous records makes it possible to assess the reliability of the resulting report.[14] Where a summary table produced through a party’s own software conflicts with the underlying raw data, the inquiry should not be confined to the table. Requiring disclosure of all software source code is not, however, necessary in every case. Limiting the request to what will clarify the technical fact can reduce the conflict between access to evidence and protection of business secrets.[15]

The functions of party-appointed and tribunal-appointed experts should be clearly defined. Meter accuracy, the feasibility of a cooling method and assumptions within a calculation model may call for expert examination; legal interpretation of the contract and determination of liability remain the arbitrators’ responsibility. The International Bar Association’s Rules address both party-appointed and tribunal-appointed experts.[16] The report’s data sources and methods should be open to examination by the opposing party. Access may be restricted, or irrelevant material separated, to protect commercial secrets.[17] Reliance on undisclosed decisive data may nevertheless create a procedural defect even where the technical conclusion is accurate. The tribunal should explain in its award why it has resolved disagreements between experts in a particular way.

An independent audit report obtained before arbitration is not automatically conclusive evidence for the tribunal. Its scope, sampling method and date of examination must be assessed.[18] If the parties contractually agreed that a technical determination would be binding, the tribunal must also examine the scope of that agreement. The contractual effect of an expert determination and the evidential weight of an expert opinion submitted during proceedings are distinct questions; international arbitral practice should preserve that distinction when addressing technical determinations.[19] Treating a measured consumption volume as binding, for example, may not resolve whether liability depends on fault or which losses are compensable. Arbitrators should neither disregard a binding finding nor attribute to a technical report adjudicative finality that the contract does not confer. The reasoning must explain the boundary between the auditor’s mandate and the relief sought in arbitration.

The consequences of missing information should not be determined without investigating why the document is unavailable. A record lost within an ordinary retention period does not signify the same conduct as data deliberately deleted after a dispute arose.[20] Arbitrators should examine the consistency of the explanation and whether other evidence supports it. Evidence obtained unlawfully may raise a separate question of admissibility. The International Bar Association’s Rules confer discretion in this respect.[21] The importance of the environmental interest does not require the admission of every document obtained covertly; the assessment must be made in light of the particular circumstances and applicable law.

II. The Tribunal’s Assessment of Damages

The starting point for an award of damages is the position the creditor would have occupied had the contract been properly performed. The Principles of International Commercial Contracts separately address full compensation, sufficient certainty of harm and foreseeability.[22] They do not constitute legislation automatically applicable to every arbitration; their relevance depends on the parties’ choice or another applicable legal basis. Additional energy charges, substitute service expenditure and necessary technical upgrading costs may be examined as separate heads of loss. A claimant’s presentation of a single aggregate figure does not relieve the tribunal of explaining the connection between each item and the breach. The same expense should not be counted twice under service interruption and repair costs, and the comparison underpinning the damages calculation must be made explicit.

Assessing loss requires a reasonable reconstruction of the economic course of events had the breach not occurred. The price of additional services purchased because a treatment unit underperformed should be adjusted for expenditure that proper contractual performance would already have required.[23] Otherwise, the claimant could use the breach to transfer ordinary operating costs to the other party. Saved expenditure, the residual value of equipment and benefits derived from a substitute transaction may be relevant to the calculation. This inquiry does not aim to undercompensate the injured party; it keeps damages within the loss actually attributable to the breach. Each deduction must rest on concrete economic evidence.[24]

Where several events contribute to the same outcome, allocating the entire loss to a single obligor requires further justification. A technical defect may have operated alongside changes to production planning or the creditor’s delay in arranging necessary maintenance.[25] The analysis should distinguish each event’s contribution to the loss and the risks assumed by the parties. Multiple sources of environmental damage may also engage a public-law liability regime, which contractual allocation does not replace. Without explaining the legal relationship underlying the claim, arbitrators should not treat the person held responsible by a public authority as necessarily bearing the ultimate economic burden.[26]

Ecological loss may extend beyond the reduction shown in an undertaking’s balance sheet. In its 2018 compensation judgment in the dispute between Costa Rica and Nicaragua, the International Court of Justice treated the loss of environmental goods and services as compensable.[27] That inter-State judgment does not create a direct cause of action in private commercial arbitration, but demonstrates that damage cannot be confined to property with a market price. Annex II to the Environmental Liability Directive likewise distinguishes primary, complementary and compensatory remediation.[28] Applying that approach in a contractual dispute requires separate identification of the claimant’s entitlement to seek relief and the scope of the obligation undertaken.

Claiming future expenditure in arbitration does not require treating invoices not yet issued as existing liabilities. The claimant should explain the legal obligation necessitating the expenditure and the technical foundation of the anticipated solution. An expert estimate must be open to scrutiny as regards its data, methodology and assumptions.[29] The feasibility and expected protective outcome of remediation options are material; Annex II to the Environmental Liability Directive provides criteria for evaluating those options.[30] A tribunal must not, however, substitute itself for the competent public authority and devise a remediation programme at large. Its task is to determine necessary and provable expenditure within the contractual claim before it. Where several methods are available, the reasons connecting the selected method to the amount awarded must be sufficiently clear to address the opposing party’s objections.

Ecosystem recovery and the restoration of an undertaking’s previous economic position may proceed at different rates. A company may mitigate its commercial loss by obtaining services from another facility while the damaged aquatic environment takes much longer to recover. Environmental remediation methods account for this continuity in the functions of natural resources.[31] A private-law claim nevertheless requires proof that the claimant has incurred, or is legally required to incur, the relevant cost. Treating a public expense for which the claimant bears no responsibility as its own receivable supplies no sufficient basis for recovery. The breadth of an ecological assessment and the scope of a right of action are different questions and require separate reasons.[32]

The time required for natural recovery makes it difficult to assume that payment alone eliminates all consequences. It does not follow that arbitrators may award compensation for environmental losses unrelated to the contract. A party that bears the cost of remediation ordered by a public authority must explain the legal basis for seeking recovery from the other party.[33] The reasonableness of measures such as purchasing substitute services or temporarily reducing operations also requires separate examination. Mitigation rules should not demand unlimited sacrifice from the creditor; their function is to prevent avoidable loss from being charged to the obligor.[34]

Claims for reputational harm call for careful scrutiny in environmental disputes. Adverse publicity does not, by itself, prove a particular amount of lost revenue. The connection between the event and consequences such as lost customers, cancelled contracts or additional financing costs should be investigated.[35] The tribunal should also examine whether public reaction arose from other causes. The existence of a legally protected interest does not justify determining the amount without explanation. If estimation is used, the limits of the data should be identified and competing influences distinguished. The visibility of an environmental breach should not become a punitive rationale that substitutes for proof.[36]

The effect of liability limitations on environmental obligations is particularly significant. Setting a very low payment for exceeding a consumption limit may make non-performance economically attractive to an operator. Nevertheless, such a clause cannot be declared invalid in advance merely because it conflicts with an environmental objective; the applicable law’s criteria for review must be identified.[37] Under English law, the inquiry in Cavendish concerns whether a secondary obligation triggered by breach is out of proportion to the innocent party’s legitimate interest.[38] That test should not be transferred unchanged to penalty provisions in other legal systems. Comparison must preserve the differences between the laws concerned.

In arbitral claims based on an agreed payment or penalty clause, the legal character of the stipulated sum is decisive. Article 7.4.13 of the Principles of International Commercial Contracts specifically addresses payments agreed for non-performance.[39] Its applicability and the conditions for any reduction must be examined within the substantive law governing the arbitration. The English decision in Cavendish presents a different assessment, focused on the disproportionality of a secondary obligation arising upon breach in relation to the innocent party’s legitimate interest.[40] A tribunal should not merge these tests as though a single international penalty regime existed. If payment is due whenever a specified consumption limit is exceeded, the relevant period, recurrence and availability of additional damages must be derived from the contract, while preventing repeated recovery for the same loss.

Insurance payments or contributions from another responsible person may affect ownership of the claim and the portion of the loss that remains uncompensated. This issue should be distinguished from the original existence of the damage. Compensation is not intended to remedy the same loss more than once.[41] Payment by an insurer does not necessarily extinguish every claim against the other party, however; subrogation or assignment must be determined under the relevant law. The tribunal should examine the identity of the person entitled to claim and the arbitration agreement’s effect in relation to that person. A payment should not be treated as automatically determining procedural standing.[42]

III. Awards of Specific Performance and Interim Relief

An award of money does not always remedy an ongoing technical deficiency. Repairing a leak, installing a measurement system or replacing contractually promised equipment may, where the relevant conditions are met, be the subject of specific performance.[43] Subject to the parties’ agreement, the English Arbitration Act 1996 permits certain orders requiring or restraining conduct and specific performance of contracts other than those relating to land.[44] Singapore’s International Arbitration Act also regulates the remedies available to arbitrators.[45] The availability of a particular measure nevertheless requires examination of the law of the seat alongside the substantive law governing the dispute and the parties’ agreement.

An order for specific performance requires the work sought to be legally and practically possible. Adding a cooling unit to an existing facility, for example, may depend on another administrative permit or the property owner’s consent. An unconditional order with a fixed deadline may be difficult to implement if these matters beyond the obligor’s control have not been assessed.[46] A need for permission does not invariably require dismissal of the performance claim: a duty to apply or complete the necessary preparations may be considered separately. The conduct ordered must correspond to the obligation undertaken and the powers available to the obligor.[47]

The enforceability of an order for specific performance depends on stating its technical objective with sufficient precision. A general direction that an operator act more responsibly towards the environment does not explain what conduct will discharge the obligation. The unit to be replaced, the completion period and the verification criterion must be identified. An expert’s role should also remain confined to technical supervision of implementation, rather than becoming authority to decide the merits afresh. The International Chamber of Commerce’s emphasis on expertise and appropriate remedies offers guidance for preparing such awards.[48] Technical detail should serve the clarity and practical implementation of the operative provisions.

The content of an award of specific performance cannot be left to the unrestricted discretion of an expert appointed later. Rules concerning tribunal-appointed experts and reasoned awards require technical assistance to be distinguished from the adjudicative function.[49] The award should identify the part of the facility to be repaired, the result to be achieved and the time for completion. An expert may assess technical compliance with those criteria, but should not redefine the obligations undertaken by the parties.[50] Performance may be divided into stages, provided the conditions for completing each stage are clear. Such an award can leave the obligor necessary technical flexibility without requiring the creditor to accept an entirely indeterminate promise of improvement. Clear operative provisions enable the protection obtained through arbitration to remain effective at enforcement.

Drought or constraints on electricity supply may require reconsideration of contractual risk allocation. An increase in cost does not, however, invariably make performance impossible. Hardship and force majeure are subject to different conditions and consequences; a request for renegotiation does not automatically suspend all obligations.[51] The conduct of the party invoking the impediment in giving notice also matters.[52] In a data centre dispute, the inquiry should address whether alternative cooling is possible, whether restrictions in the relevant basin were foreseeable and whether the contract allocated that risk. A general reference to a climatic event cannot replace these specific assessments.

New circumstances arising during continuing performance should be considered alongside, but separately from, the consequences of an earlier breach. A later drought does not cure inaccurate measurement records from an earlier period. Equally, past fault by the obligor does not extinguish every defence concerning future impediments.[53] Arbitrators should distinguish the relevant periods and identify when each obligation was capable of performance. A request for contractual adaptation and a claim for past losses may therefore rest on different calculations. Resolving past liability and maintaining the future relationship should not be combined in a single undifferentiated amount.[54]

Evidence may disappear or damage worsen while a final award is awaited. Interim relief may involve preserving meter data, keeping particular equipment available for inspection or restricting a hazardous operation within the parties’ control. The International Chamber of Commerce’s 2026 Arbitration Rules address the tribunal’s power to order interim measures and the compatibility of an application to a court with the arbitration agreement.[55] A measure should be proportionate and connected to the claim. An order determining the operation of a third party’s network raises jurisdictional questions different from an order regulating a party’s conduct at its own facility.

Urgency before the tribunal is constituted may be addressed under the same Rules’ emergency arbitrator provisions.[56] Speed of decision does not mean that the resulting order can be enforced through identical procedures in every country. The extent of court assistance becomes especially important where physical intervention or a third party’s cooperation is needed. The English Arbitration Act’s provisions on supportive court powers offer a comparative illustration.[57] Successful interim protection depends not only on prompt application but also on correctly identifying who controls the requested action and which authority can secure it.

Dividing arbitral proceedings into phases should account for the relationship between interpretation of the environmental undertaking and assessment of loss. Examining the meaning of a particular indicator or the period of breach first may narrow the scope of a subsequent expert report. The International Chamber of Commerce’s Rules permit case management and scheduling after consultation with the parties.[58] Separate phases may nevertheless increase costs if they require the same witness to testify repeatedly or the same technical data to be examined again. Arbitrators should explain which issue will be decided first and its effect on subsequent phases. The English Arbitration Act’s fairness provision is also relevant comparatively to preserving each party’s opportunity to address the case.[59] Procedural efficiency must not become a restriction preventing presentation of a decisive claim or defence.

Consider a hypothetical treatment contract under which a contractor fails to deliver the required quality and the operator consequently purchases water externally. An initial calculation might treat the price of all water purchased as loss. Proper performance would, however, still have entailed expenditure on energy, chemicals and maintenance. The actual additional burden emerges from that comparison. If the operator rejected a reasonable temporary solution after learning of the defect, subsequent expenditure may also require different treatment. Conversely, the contractor’s offer of a free repair might require a prolonged production shutdown, which could separately justify rejection. In this example, the monetary claim, technical correction and mitigation conduct are connected but are not the same question. Explaining each separately in the award helps prevent both calculation errors and the unnecessary exclusion of one remedy by another. The outcome follows from the demonstrable relationship between the promised performance and proven loss, rather than from the scale of the environmental objective alone.

Protection through international arbitration for breaches of environmental commitments depends on distinguishing the burden of proof from access to evidence and identifying the appropriate remedy. A respondent’s possession of technical data may require procedural measures, but is insufficient to presume every element of liability. Claims for damages, specific performance and interim relief likewise do not depend on identical legal conditions. The award should identify which facts are established by which evidence, which legal rules apply and why the relief sought is granted or refused. The International Chamber of Commerce’s approach to reasoned awards and enforceability illustrates the importance of these connections.[60] Environmental protection can thereby be given effect through adjudication of the specific obligations undertaken by the parties, and the award can translate technical assessment into a legally enforceable outcome.

Necip İlker Karaoğlan is a legal professional whose work spans international arbitration, maritime law and comparative law. His activities include legal research, legal publications and editorial work.

Footnotes

1. UNIDROIT, Principles of International Commercial Contracts 2016, Articles 5.1.4–5.1.5 and 7.1.1.

2. International Chamber of Commerce, Resolving Climate Change Related Disputes through Arbitration and ADR, ICC Publication 999 ENG (2019), Section II, pp. 8–12.

3. International Bar Association, IBA Rules on the Taking of Evidence in International Arbitration, adopted 17 December 2020, Articles 1–2.

4. International Chamber of Commerce, Arbitration Rules, in force from 1 June 2026, Article 23(4).

5. IBA Rules on the Taking of Evidence (2020) (see n. 3), Preamble; Article 1.

6. United Nations Commission on International Trade Law, UNCITRAL Arbitration Rules (2021), Article 27(1).

7. International Bar Association, Commentary on the Revised Text of the 2020 IBA Rules on the Taking of Evidence in International Arbitration (2021), Commentary on Articles 2–3.

8. United Nations Convention on Contracts for the International Sale of Goods, Vienna, 11 April 1980, Articles 35–36, for contracts within its scope.

9. UNIDROIT Principles 2016 (see n. 1), Article 7.1.2.

10. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 3(3).

11. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 9(6)–(7).

12. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 5(2)(e).

13. Commission Delegated Regulation (EU) 2024/1364 of 14 March 2024 on the first phase of the establishment of a common Union rating scheme for data centres, Annex II, measurement methodology.

14. IBA Rules on the Taking of Evidence (2020) (see n. 3), Definitions, Document; Article 3(12).

15. IBA Rules on the Taking of Evidence (2020) (see n. 3), Articles 3(3) and 9(2)(e).

16. IBA Rules on the Taking of Evidence (2020) (see n. 3), Articles 5(2) and 6.

17. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 9(2)(e) and 9(5).

18. IBA Rules on the Taking of Evidence (2020) (see n. 3), Articles 5–6.

19. International Chamber of Commerce, Climate Change Related Disputes (2019) (see n. 2), Section V.A.4, p. 25.

20. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 9(2)(d) and 9(6).

21. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 9(3).

22. UNIDROIT Principles 2016 (see n. 1), Articles 7.4.2–7.4.4.

23. UNIDROIT Principles 2016 (see n. 1), Article 7.4.2.

24. UNIDROIT Principles 2016 (see n. 1), Articles 7.4.5–7.4.6.

25. UNIDROIT Principles 2016 (see n. 1), Article 7.4.7.

26. Directive 2004/35/EC of the European Parliament and of the Council of 21 April 2004 on environmental liability with regard to the prevention and remedying of environmental damage, Articles 8–9.

27. International Court of Justice, Certain Activities Carried Out by Nicaragua in the Border Area (Costa Rica v. Nicaragua), Compensation, Judgment of 2 February 2018, I.C.J. Reports 2018, p. 15, Paragraphs 41–43.

28. Directive 2004/35/EC (see n. 26), Annex II, section 1.

29. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 5(2)(e).

30. Directive 2004/35/EC (see n. 26), Annex II, sections 1.2–1.3.

31. Directive 2004/35/EC (see n. 26), Annex II, definitions of complementary and compensatory remediation.

32. Certain Activities, Compensation (2018) (see n. 27), Paragraphs 41–43; inter-State context.

33. Directive 2004/35/EC (see n. 26), Articles 3(3), 7 and 8.

34. UNIDROIT Principles 2016 (see n. 1), Article 7.4.8.

35. UNIDROIT Principles 2016 (see n. 1), Articles 7.4.2–7.4.4.

36. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 9(1).

37. UNIDROIT Principles 2016 (see n. 1), Article 7.1.6.

38. UK Supreme Court, Cavendish Square Holding BV v Talal El Makdessi; ParkingEye Ltd v Beavis [2015] UKSC 67, Paragraphs 32–33.

39. UNIDROIT Principles 2016 (see n. 1), Article 7.4.13.

40. Cavendish; ParkingEye [2015] UKSC 67 (see n. 38), Paragraphs 32–33.

41. UNIDROIT Principles 2016 (see n. 1), Article 7.4.2.

42. Convention on the Recognition and Enforcement of Foreign Arbitral Awards, New York, 10 June 1958, Article II; Article V(1)(a).

43. UNIDROIT Principles 2016 (see n. 1), Articles 7.2.2–7.2.3.

44. United Kingdom, Arbitration Act 1996, as amended, Section 48(1)–(5).

45. Singapore, International Arbitration Act 1994, Section 12(5).

46. UNIDROIT Principles 2016 (see n. 1), Article 7.2.2(a)–(b).

47. Arbitration Act 1996 (see n. 44), Section 48(5).

48. International Chamber of Commerce, Climate Change Related Disputes (2019) (see n. 2), Section V.A, pp. 19–25.

49. ICC Arbitration Rules (2026) (see n. 4), Articles 26(3) and 35(2).

50. IBA Rules on the Taking of Evidence (2020) (see n. 3), Article 6.

51. UNIDROIT Principles 2016 (see n. 1), Articles 6.2.1–6.2.3.

52. UNIDROIT Principles 2016 (see n. 1), Article 7.1.7(3).

53. UNIDROIT Principles 2016 (see n. 1), Articles 6.2.2 and 7.1.7.

54. UNIDROIT Principles 2016 (see n. 1), Articles 7.3.5 and 7.4.1.

55. ICC Arbitration Rules (2026) (see n. 4), Article 29.

56. ICC Arbitration Rules (2026) (see n. 4), Article 31; Appendix IV.

57. Arbitration Act 1996 (see n. 44), Section 44.

58. ICC Arbitration Rules (2026) (see n. 4), Articles 23–24.

59. Arbitration Act 1996 (see n. 44), Section 33.

60. ICC Arbitration Rules (2026) (see n. 4), Articles 35(2) and 46.