Resolving disputes over water and energy use in data centres through arbitration requires identifying the contractual claim to which an environmental obligation gives rise. An interruption of electricity supply, a reduction in the water allocated for cooling, or a breach of an efficiency guarantee may affect distinct contractual relationships within the same investment. The International Energy Agency’s assessment of electricity demand from data centres demonstrates the growing economic significance of these relationships.[1] The consumption scenarios in Lawrence Berkeley National Laboratory’s June 2026 update likewise require long-term supply commitments to be assessed against the availability of resources.[2] For arbitration, the decisive issue is how these technical and economic conditions translate into obligations, defences and claims for relief that arbitrators can adjudicate. Growth in the sector does not, by itself, establish arbitral jurisdiction or a ground of liability.
Arbitration’s legal function in this field is to determine the allocation of responsibility under the contracts that enable a data centre to operate. The International Chamber of Commerce’s report on climate change-related disputes demonstrates that environmental issues can be addressed in arbitrations arising from existing commercial contracts.[3] This does not justify assuming that every water or energy issue can be brought within a single proceeding. The operator’s obligation to provide uninterrupted service to its customer, its claim against an energy supplier, and its duties towards the public authorities arise from separate legal relationships. The analysis must begin by establishing which of those relationships the arbitration agreement covers. Regulatory provisions may then impose binding limits that arbitrators must consider when interpreting the contract and determining the relief sought. Arbitration’s suitability depends as much on establishing these distinctions at the outset as on access to technical expertise.
I. The Arbitration Agreement and the Scope of the Dispute
If an arbitration clause in a data centre contract is confined to payment of service charges, its application to claims arising from water and energy commitments may be contested. The Convention on the Recognition and Enforcement of Foreign Arbitral Awards, commonly known as the New York Convention, recognises agreements to arbitrate existing or future disputes arising out of a defined legal relationship.[4] Consumption guarantees, reporting duties, cost allocation and claims arising from termination should therefore be addressed within a clearly defined scope. Selecting institutional rules does not replace the parties’ agreement to arbitrate. The International Chamber of Commerce’s 2026 Arbitration Rules likewise provide for scrutiny of the existence, validity and scope of the arbitration agreement.[5] Even a broadly drafted clause does not automatically transfer a public authority’s licensing powers to arbitrators.
In data centre projects involving several contracts, an undertaking to achieve a specified result under the principal operating agreement and a subcontractor’s obligation of best efforts may entail different standards of liability.[6] Arbitration adds a further concern: the fragmentation of proceedings. A customer’s claim against an operator and the operator’s recourse claim against a technical contractor cannot automatically be heard by the same tribunal. The International Chamber of Commerce’s 2026 Rules prescribe distinct conditions for joinder, claims under multiple contracts and consolidation.[7] Compatible choices of arbitral institution, seat and scope when drafting the contracts may reduce this risk. Procedural coordination nevertheless does not make each respondent’s substantive liability identical. A tribunal’s examination of shared technical facts must be distinguished from treating obligations under different contracts as interchangeable.
Termination of the principal contract does not invariably render its arbitration clause ineffective. Subject to the parties’ agreement otherwise, the separability provision of the English Arbitration Act requires the arbitration agreement to be considered independently of the invalidity or ineffectiveness of the principal contract.[8] The International Chamber of Commerce’s Rules similarly recognise that, where a valid arbitration agreement exists, an allegation that the principal contract is invalid does not automatically extinguish arbitral jurisdiction.[9] The loss of an operating licence, termination of a supply contract, or a challenge to the validity of technical acceptance at a data centre must be considered in light of this distinction. A tribunal’s initial determination that the arbitration agreement is valid does not establish the merits of every claim arising from an environmental undertaking. Jurisdiction and liability remain separate questions.
A properly drafted dispute resolution clause can distinguish a disagreement over measurement from a dispute over legal responsibility. The parties may agree first to compare technical records, then to obtain an expert opinion, and finally to refer unresolved claims to arbitration.[10] If these preliminary stages are indefinite or lack clear requirements, however, access to adjudication may be delayed in practice. The contract should specify when the next stage becomes available following notification and preserve access to urgent relief. An inability to appoint an expert, or one party’s failure to attend a meeting, should not suspend resolution indefinitely. A contractual sequence is valuable insofar as it facilitates settlement or adjudication; it should not operate as an obstacle that deprives the right to bring a claim of practical effect.[11]
Choosing the seat of arbitration is distinct from choosing the data centre’s physical location. Parties may agree to arbitrate in another country while providing for an inspection at the facility or the submission of technical documents in a different language. The International Chamber of Commerce’s Rules contain separate provisions on the place of arbitration, procedure and language.[12] Holding a hearing at the facility does not, by itself, change the arbitral seat. The confidentiality of technical operations, experts’ access to the premises and translation costs should be considered when the contract is concluded. The seat’s relationship with the supportive and supervisory jurisdiction of national courts must not be reduced to geographical convenience. The English Arbitration Act’s provisions on court assistance offer a comparative illustration of that relationship.[13]
The distinction between an expert determination and an arbitral award directly affects the function of the arbitration clause in consumption disputes. The International Chamber of Commerce’s report separately addresses expert examination and technical determination.[14] Parties may have agreed that an expert will determine meter accuracy with binding effect; this does not mean that the expert has also been authorised to adjudicate liability and compensation. The tribunal must interpret the contract to establish the extent to which the technical finding binds it.[15] Clear provisions on the grounds for challenging an expert report, its finality and the referral of legal claims to arbitration may reduce the need to revisit the same measurement. Expertise can thereby narrow the issues requiring adjudication without displacing arbitration.
II. Applicable Law and Environmental Obligations before the Tribunal
Choosing the law governing the merits is separate from selecting the seat of arbitration. Article 22 of the International Chamber of Commerce’s 2026 Arbitration Rules permits the parties to choose rules of law; absent a choice, the tribunal applies the rules of law it considers appropriate and takes account of the contractual provisions and relevant trade usages.[16] The fact that a data centre operator is an international company does not require its environmental commitments to be assessed independently of national law. The tribunal should examine the water abstraction permit, obligations concerning electricity supply and the consumption guarantee without treating them as having a single legal basis. Nor can authority to decide freely according to equity be inferred from the importance of environmental protection. Such authority depends on the separate authorisation required under the applicable arbitral regime.
The Rome I Regulation must be placed carefully within an arbitral analysis of choice of law. It excludes arbitration agreements from its scope and separately addresses overriding mandatory provisions.[17] These provisions do not establish that every tribunal must follow the same conflict-of-laws method; the basis for the method adopted must be explained within the relevant arbitral framework. The law governing the principal contract, the law applicable to the arbitration agreement and the administrative legislation at the facility’s location perform different functions. The distinction between directives and regulations under Article 288 of the Treaty on the Functioning of the European Union must also be maintained.[18] When applying a directive’s provisions to a claim between private parties, the tribunal should identify the national implementing legislation, contractual incorporation or other legal basis relied upon. Technical relevance does not dispense with the inquiry into legal applicability.
Identifying the source of a reporting duty before the tribunal requires examining the interaction between European Union legislation and the contract. The Energy Efficiency Directive provides for the disclosure of information concerning data centres with an installed information technology power demand of at least 500 kilowatts.[19] Commission Delegated Regulation (EU) 2024/1364 specifies the information to be communicated to the European database and the relevant calculation methods.[20] A claimant’s entitlement in arbitration does not, however, arise automatically from a report submitted to a public authority. A customer may have contractually required delivery of the same information or a guarantee of its accuracy. The tribunal must separately explain a breach of the public reporting requirement and a breach of the duty owed to the customer. A report complying with legislation is likewise not conclusive evidence that a more demanding contractual performance guarantee has been satisfied.
In a colocation facility, customers may operate their own servers while the building operator provides shared cooling. Total consumption may then be allocated among customers by occupied space, actual measurement or predetermined technical coefficients. The chosen method need not be identical to that used for regulatory reporting, but the difference should be explained.[21] A change to the allocation formula as the business expands may alter the economic balance of existing contracts. Shared operating costs, compliance with environmental targets and publicly reported consumption should therefore be treated as three separate calculations. A result obtained in one calculation should not be regarded as conclusive evidence of accuracy in another.[22]
Power usage effectiveness and water usage effectiveness relate particular facility inputs to the energy consumption of information technology equipment.[23] Improvement in these ratios does not necessarily establish a reduction in total resource use. In arbitration, the dispute may turn on whether the parties undertook to achieve efficiency per unit or a limit on absolute consumption. Where the claimant relies on total annual abstraction and the respondent invokes an improved efficiency ratio, the tribunal must first identify the subject matter of the obligation. A technical expert’s calculations cannot replace this adjudicative task of contractual interpretation. Unless the award specifies the relevant indicator, measurement period and capacity assumption, the same technical data may be used to support conflicting legal conclusions. An assertion of environmental achievement must therefore be connected to the contractual criterion on which the claim rests.
In arbitral proceedings, the physical boundary of measurement must be considered alongside the contractual terms defining the obligation. Excluding backup generators, shared buildings or externally supplied cooling can produce different consumption figures.[24] The tribunal’s task is not invariably to select the technically most comprehensive calculation, but to identify the calculation required by the parties’ undertaking. It should examine whether changes to technical schedules were agreed and what significance previous practice has for interpreting the contract.[25] A method subsequently adopted by one party cannot replace the agreed calculation merely because it is scientifically defensible. Conversely, where the contract lacks an express provision, arbitrators should give specific reasons for an interpretation consistent with its purpose.
Annual averages may conceal the legal significance of short periods of intensive use. A sharp increase in water abstraction during a particular month, for example, is not rendered compliant with the permit applicable at that time merely because lower consumption during the rest of the year offsets it.[26] A contract may accordingly distinguish a daily maximum, a seasonal threshold and an annual target. This cannot be prescribed as a mandatory approach for every contract: it should be justified by the characteristics of the basin and the structure of the permit. Where the commercial accounting period differs from the authority’s monitoring period, compliance must be assessed separately for each interval.[27]
Water accounting should distinguish the volume entering the facility, the amount returned to the basin and indirect use associated with electricity generation. Berkeley Laboratory’s research assesses the direct and indirect water impacts of data centres separately.[28] A contract may rely exclusively on the meter at the facility boundary, but that choice cannot be represented as also capturing impacts outside it. Equally, water replenishment undertaken in another basin does not prove compliance with the abstraction limit at the operating site. Clarity about the accounting boundary determines both the accuracy of environmental representations and the facts that will need to be proved in a subsequent claim.
Establishing a baseline is particularly important when drafting resource efficiency provisions. Results obtained during acceptance testing of a new facility may not represent its ordinary workload in continuous operation. By converting a favourable ratio achieved at low occupancy into a long-term guarantee, an operator may also assume the consequences of subsequent capacity growth.[29] The contract should therefore specify the workload at which the baseline was measured and the circumstances in which expansion justifies reassessment. Correcting every subsequent deviation by adjusting the baseline weakens the guarantee’s substance. Revising the measurement basis should not confer unrestricted authority to eliminate a breach retrospectively.[30]
The scope of an environmental undertaking in arbitration cannot be inferred solely from the contract’s title. Consumption limits stated during negotiations, letters providing technical assurances and the parties’ subsequent conduct may be relevant to interpretation.[31] Arbitrators should distinguish an assurance given for a particular facility from a long-term target covering a company’s entire operations. Common instruments concerning international commercial contracts provide a basis for comparing the legal grounds of that interpretative exercise.[32] Interpretation should nevertheless not create an obligation to achieve a result that the parties never undertook. The reasoning should identify the representation on which the claimant based its investment decision, how that representation entered the contract and which risk the respondent accepted. Arbitration can then address breaches of specific undertakings without converting general sustainability statements into unlimited liability.
Whether environmental language in a contract is binding should be assessed by reference to the legal significance of the obligations expressed. Undertaking not to exceed a specified consumption threshold is different from promising to take reasonable measures to conserve resources. The International Institute for the Unification of Private Law’s Principles of International Commercial Contracts distinguish obligations to achieve a specific result from obligations of best efforts.[33] These Principles are not legislation automatically applicable to every international contract. Their use must be considered in light of the parties’ choice and the legal framework governing the dispute; they are not an independent source of authority to displace mandatory rules.[34]
A tribunal should distinguish a defence based on compliance with permits from one based on contractual performance. If an operator undertakes to use less water than the legally permitted volume, the absence of an administrative sanction does not exclude contractual liability.[35] Conversely, an assurance of uninterrupted service given to a customer cannot make abstraction beyond the permit lawful. The relationship between the governing law of the contract and overriding mandatory provisions becomes material at this point.[36] Arbitrators should examine which party bears the risk of a reduced permit and whether the performance sought is compatible with restrictions currently in force. An order for performance that disregards administrative regulation may appear to satisfy the commercial claim yet create difficulties when implementation is attempted.
Continuity of electricity supply and its environmental attributes are distinct obligations. Producing a certificate associated with renewable energy does not, by itself, establish physical supply at a particular hour; electricity flows and contractual allocation in emissions accounting are not the same fact.[37] Where parties require both security of supply and a particular environmental attribute, they should provide separate verification procedures. An obligation to furnish a replacement certificate if the supplier’s certificate becomes invalid must not be confused with liability for an interruption of service. Unless the indicator’s contractual function is clear, it may remain disputed whether a deficiency in environmental attributes is a non-conformity remediable by a price reduction or amounts to a fundamental breach.[38]
Waste heat utilisation offers a further means of translating environmental expectations into concrete obligations. The Energy Efficiency Directive regulates waste heat utilisation by data centres with a total rated energy input exceeding one megawatt, subject to conditions concerning technical or economic feasibility.[39] Where heat is to be supplied to a municipal network, a dispute may arise from factors other than the operator’s production capacity. The recipient’s failure to complete the connection, a seasonal reduction in demand or failure to achieve the required temperature may also affect performance. A general recovery undertaking leaves the allocation of responsibility uncertain unless it identifies the delivery point, usable temperature range and consequences of network interruptions.
In waste heat transfers, it matters whether a delivery shortfall results from technical inadequacy or the recipient’s capacity to accept the heat. If a data centre offers heat at the specified temperature but the district network cannot receive it, allocating the entire contractual burden to the producer may not always be appropriate.[40] Capacity readiness, maintenance schedules and acceptance obligations should therefore be addressed reciprocally. A recipient’s failure to complete its preparations cannot be assessed in the same way as an operator’s failure to install any heat recovery system. The parties’ cooperation directly affects achievement of the environmental objective; a contract focused exclusively on one party’s technical performance is insufficient.[41]
III. Determining Liability and Allocating Contractual Risks in Arbitration
The legality of water use cannot be secured solely through a supply contract between the parties. Alongside objectives concerning the status of water bodies, the Water Framework Directive provides for controls over abstraction and, in specified circumstances, prior authorisation.[42] In Weser, the Court of Justice of the European Union restricted the authorisation of projects liable to cause deterioration in the status of a water body, subject to the conditions governing derogations.[43] A private supplier’s undertaking to deliver a specified volume therefore does not mean that the volume can lawfully be abstracted in all circumstances. The contract should expressly address the scope of existing permits and the parties’ rights if they are restricted.
A long-term agreement with a water supplier cannot freeze a public authority’s future allocation decisions; regulatory powers over abstraction remain in place.[44] The issue capable of being referred to arbitration is which party bears the economic risk of a reduced allocation under the contract. Expenditure on alternative sources, reduced capacity or relocation of services to another facility may be examined on that basis. A tribunal should not treat the disclosure conduct of a party already aware of a restriction as equivalent to a new measure that neither party could foresee. Where their conditions are met, provisions on good faith and hardship may support this distinction.[45] A request for adaptation nevertheless does not automatically transfer all losses to the other party or suspend the contract throughout the proceedings.
Combining the supply of technical equipment with continuing operational services may also raise questions about the legal characterisation of the contract. Article 3 of the United Nations Convention on Contracts for the International Sale of Goods draws a specific boundary by reference to the predominance of the service element.[46] Server sales, the installation of cooling infrastructure and the provision of cloud capacity should consequently not be assumed to fall under identical rules. Identifying obligations separately does more than improve drafting: it clarifies against whom a non-conformity claim may be brought and which remedies are available. In particular, conformity at delivery must be distinguished from performance to be maintained throughout an extended operating period.
In arbitration, a request for adaptation based on a legislative change is not resolved merely by establishing that the change occurred. The tribunal must interpret the relevant contractual clause to determine the period and categories of expenditure it covers.[47] Maintenance that the operator was required to perform from the outset should not be passed to the other party as a newly incurred compliance cost. Nor should a new water restriction be assumed to justify an increase in the entire service charge: a connection must be established between the change and the amount claimed. The application of hardship provisions likewise depends on their own conditions and prescribed consequences.[48] Arbitrators should treat compensation for past losses, prospective price adjustment and termination as distinct claims, avoiding a restructuring of the contract beyond the relief requested.
A payment claim before arbitrators that relies on the Environmental Liability Directive requires particular clarity about its legal basis. Liability cannot be imposed merely because a data centre is operated, without examining the activity’s inclusion within the Directive’s scope, the nature of the damage and causation.[49] The Directive also expressly states that it does not confer on private parties a right to compensation.[50] The operator’s remediation obligations towards the authorities must therefore be distinguished from a customer’s contractual claim in arbitration. The claimant should identify the contractual provision or applicable legal rule that permits recovery of the expenditure from the other party. The tribunal may consider costs assessed by a public authority as evidence, but their existence does not authorise a liability ruling binding everyone outside the arbitration agreement.
This distinction is decisive for recourse against a contractor or infrastructure provider. An authority’s claim for remediation costs against the operator does not necessarily require the ultimate economic burden to remain with that operator. Where the relevant contract and law permit, recourse may be available against the contractor that installed a defective cooling system or the consultant that supplied inaccurate technical data. The Directive’s provisions on costs and competent authorities preserve the independence of public enforcement.[51] A recourse clause does not suspend that process; it determines which part of an amount paid can be allocated to the other party by reference to the responsibilities each assumed. The scope of the breach and that of the expenditure must be established separately.
Access to environmental data can be regulated alongside commercial confidentiality, without subjecting all information to the same degree of protection. Customer lists and security architecture concern interests different from those associated with total water abstraction. Exceptions to disclosure of environmental information held by public authorities require separate assessment.[52] While limiting access to protect legitimate secrets, a contract should expressly preserve legally required reporting. An audit right should not become an unrestricted means of learning about a competitor’s business, and a confidentiality clause should not prevent investigation of compliance with environmental obligations. These objectives can be reconciled through specific categories of documents.[53]
Retaining technical records may be stipulated as a separate ancillary obligation. A contractual consumption limit becomes harder to verify if measurement data may be deleted after only a few months. The retention period should be connected to the accounting period, reporting timetable and period within which a potential claim may be brought.[54] Longer retention is not invariably preferable, however. Record integrity, access authorisation and the history of corrections also require protection. A table prepared retrospectively may not have the same evidential value as a contemporaneous meter record. Regulating data management contractually can narrow subsequent disputes about proof.[55]
A tribunal equipped with environmental and technical expertise may make a data centre arbitration clause more effective. Selection should combine competence to understand measurement disputes with independence and impartiality; the International Chamber of Commerce’s report specifically addresses this need for expertise.[56] Technical knowledge does not justify applying, without explanation, a calculation method that the parties have had no opportunity to address. Examining a particular consumption period, a definition in a technical schedule or a cost allocation issue first may narrow the remaining claims. The benefit depends on case management reflecting the dispute’s actual complexity.[57] Where a continuing service relationship must survive the dispute, arbitrators should also consider the effect of the requested relief on future performance.
In a hypothetical arbitration, a customer might allege that the summer water limit was exceeded even though the annual consumption indicator was satisfied. The operator might respond that the waste heat recipient delayed the connection and that the energy supplier failed to provide a contractual certificate. A single general assessment of sustainability would not resolve these claims. The relevant measurement period and calculation method must first be identified, followed by the obligations assumed by each party.[58] Duties of cooperation, undertakings to achieve a specified result and obligations of best efforts may give rise to different assessments of liability.[59] Moreover, a respondent’s recourse claim against a party to another contract cannot be determined unless the conditions for that party’s participation in the existing arbitration are satisfied. Distinguishing these matters enables the award to reflect that a technically integrated project comprises legally separate contractual relationships.
Effective arbitration of water and energy disputes in data centres requires more than mentioning environmental legislation as background. The analysis must explain how that legislation affects the scope of contractual obligations, the validity of defences and the legality of the performance sought. A valid arbitration agreement covering the parties and claims is the necessary starting point.[60] Measurement provisions, adaptation clauses and procedural arrangements for multiple contracts can make that agreement effective. Arbitrators can resolve the dispute insofar as they connect technical consumption data to a legal obligation and a breach to identifiable relief. This approach permits adjudication of commercial liabilities arising from resource use in data centres without converting arbitration into a general environmental supervisory authority.
Necip İlker Karaoğlan is a legal professional whose work spans international arbitration, maritime law and comparative law. His activities include legal research, legal publications and editorial work.
Footnotes
1. International Energy Agency, Energy and AI (2025), Executive summary.
2. Sarah Josephine Smith et al., United States Data Center Energy Usage Report: 2025 Update, Lawrence Berkeley National Laboratory (June 2026), Abstract and Reference Case.
3. International Chamber of Commerce, Resolving Climate Change Related Disputes through Arbitration and ADR, ICC Publication 999 ENG (2019), Sections II–III, pp. 8–15.
4. Convention on the Recognition and Enforcement of Foreign Arbitral Awards, New York, 10 June 1958, Article II(1).
5. International Chamber of Commerce, Arbitration Rules, in force from 1 June 2026, Article 7.
6. UNIDROIT, Principles of International Commercial Contracts 2016, Articles 5.1.4–5.1.5.
7. ICC Arbitration Rules (2026) (see n. 5), Articles 8–11.
8. United Kingdom, Arbitration Act 1996, as amended, Section 7.
9. ICC Arbitration Rules (2026) (see n. 5), Article 7(8).
10. International Chamber of Commerce, Climate Change Related Disputes (2019) (see n. 3), Section V.B.1, pp. 28–34.
11. ICC Arbitration Rules (2026) (see n. 5), Articles 29 and 31.
12. ICC Arbitration Rules (2026) (see n. 5), Articles 19–21.
13. Arbitration Act 1996 (see n. 8), Section 44.
14. International Chamber of Commerce, Climate Change Related Disputes (2019) (see n. 3), Section V.A.4, p. 25; Section V.B.1(ii), p. 32.
15. UNIDROIT Principles 2016 (see n. 6), Articles 4.1–4.3.
16. ICC Arbitration Rules (2026) (see n. 5), Article 22.
17. Regulation (EC) No 593/2008 of 17 June 2008 on the law applicable to contractual obligations (Rome I), Articles 1(2)(e) and 9.
18. Consolidated Version of the Treaty on the Functioning of the European Union, Article 288.
19. Directive (EU) 2023/1791 of the European Parliament and of the Council of 13 September 2023 on energy efficiency, Article 12(1) and Annex VII.
20. Commission Delegated Regulation (EU) 2024/1364 of 14 March 2024 on the first phase of the establishment of a common Union rating scheme for data centres, Articles 1 and 3; Annexes I–II.
21. Delegated Regulation (EU) 2024/1364 (see n. 20), Article 2 and Annex I.
22. World Resources Institute and World Business Council for Sustainable Development, GHG Protocol Scope 2 Guidance (2015), Chapter 5, section 5.2.1.
23. Delegated Regulation (EU) 2024/1364 (see n. 20), Annex III, points (a)–(b).
24. Delegated Regulation (EU) 2024/1364 (see n. 20), Annex II.
25. UNIDROIT Principles 2016 (see n. 6), Articles 4.1–4.3.
26. Directive 2000/60/EC of the European Parliament and of the Council of 23 October 2000 establishing a framework for Community action in the field of water policy, Articles 4 and 11.
27. Court of Justice of the European Union, Bund für Umwelt und Naturschutz Deutschland eV v Bundesrepublik Deutschland, Case C-461/13, EU:C:2015:433, Judgment of 1 July 2015, Operative part, points 1–2.
28. Arman Shehabi et al., 2024 United States Data Center Energy Usage Report, Lawrence Berkeley National Laboratory (2024), Analysis of direct and indirect water use.
29. Delegated Regulation (EU) 2024/1364 (see n. 20), Annexes II–III.
30. UNIDROIT Principles 2016 (see n. 6), Article 5.1.5.
31. UNIDROIT Principles 2016 (see n. 6), Article 4.3.
32. UNCITRAL, HCCH and UNIDROIT, Legal Guide to Uniform Instruments in the Area of International Commercial Contracts, with a Focus on Sales (2020), Discussion of contract interpretation and the UNIDROIT Principles.
33. UNIDROIT Principles 2016 (see n. 6), Articles 5.1.4–5.1.5.
34. UNIDROIT Principles 2016 (see n. 6), Preamble; Article 1.4.
35. UNIDROIT Principles 2016 (see n. 6), Articles 1.1 and 1.3.
36. Rome I Regulation (see n. 17), Article 9.
37. GHG Protocol Scope 2 Guidance (2015) (see n. 22), Chapter 4, especially section 4.1.2.
38. UNIDROIT Principles 2016 (see n. 6), Articles 5.1.4–5.1.6.
39. Directive (EU) 2023/1791 (see n. 19), Article 26(6).
40. Directive (EU) 2023/1791 (see n. 19), Article 26(6).
41. UNIDROIT Principles 2016 (see n. 6), Articles 5.1.3 and 7.1.2.
42. Directive 2000/60/EC (see n. 26), Articles 4 and 11(3)(e).
43. Bund für Umwelt und Naturschutz Deutschland, C-461/13 (see n. 27), Operative part, point 1.
44. Directive 2000/60/EC (see n. 26), Article 11(3)(e).
45. UNIDROIT Principles 2016 (see n. 6), Articles 1.7 and 6.2.2.
46. United Nations Convention on Contracts for the International Sale of Goods, Vienna, 11 April 1980, Article 3(2).
47. UNIDROIT Principles 2016 (see n. 6), Articles 4.1–4.3.
48. UNIDROIT Principles 2016 (see n. 6), Article 6.2.3.
49. Directive 2004/35/EC of the European Parliament and of the Council of 21 April 2004 on environmental liability with regard to the prevention and remedying of environmental damage, Articles 2–3; Annex III.
50. Directive 2004/35/EC (see n. 49), Article 3(3).
51. Directive 2004/35/EC (see n. 49), Articles 8 and 11.
52. Directive 2003/4/EC of the European Parliament and of the Council of 28 January 2003 on public access to environmental information, Article 4(2).
53. International Bar Association, IBA Rules on the Taking of Evidence in International Arbitration, adopted 17 December 2020, Article 9(5).
54. Delegated Regulation (EU) 2024/1364 (see n. 20), Article 3 and Annex II.
55. IBA Rules on the Taking of Evidence (2020) (see n. 53), Articles 3 and 9(6).
56. International Chamber of Commerce, Climate Change Related Disputes (2019) (see n. 3), Section V.A, pp. 19–25.
57. ICC Arbitration Rules (2026) (see n. 5), Articles 23–24.
58. Delegated Regulation (EU) 2024/1364 (see n. 20), Annexes II–III.
59. UNIDROIT Principles 2016 (see n. 6), Articles 5.1.3–5.1.5.
60. New York Convention (1958) (see n. 4), Article II(1).